Dearborn Public Schools

Project Size:
$75,000,000

Square Feet:
multiple buildings

Contract Type:
Construction Management (CM)

Owner:
Dearborn Public Schools

Architect:
TMP Associates
Stantec

Phase I – Summer 2014 June 15 thru August 28 – The summer work consisted of a new concession and team rooms at Edsel Ford High School. Renovation of the Dearborn Heights Center, (6) roofing replacements, (6) parking lot replacements, (22) schools with miscellaneous construction including HVAC upgrades, flooring replacement, lockers, painting, office expansion, and digital
signage.
Phase II – Fall 2014 thru summer 2015 – The second phase includes building additions to (3) elementary schools (45,000 s.f.) and a concession/grandstand replacement at Fordson High School. We will also be breaking ground on Phase III which consists of (3) additions (32,000 s.f.) to middle schools. The summer portion will consist of (9) roofing replacements, (6) asphalt replacements, (15) schools with miscellaneous construction including HVAC upgrades, window replacements, office, auditorium, locker rooms, class room renovations, and (17) schools with partial furniture removal and replacement.
Phase III Fall 2015 thru summer 2016 – The third phase will consist of completing the (3) additions and renovations started in phase II, renovation of the Administrative Service Center, and miscellaneous projects being discussed to utilize the remaining $3.5 million contingency.
Additional Services:
Clark Construction is also managing and supporting the district wide card access control installation, $5 million wireless access upgrade in (34) facilities, $6 million computer/IT upgrade package, and continual support services for the district.